Here are the latest status updates on our roof project:
Roofing work is underway on both the Langdell north and south lower roofs over the classrooms, continuing through the look-ahead period.
During the week of June 21:
- Masonry repairs and restoration to the head house areas above the Langdell north and south roofs will begin.
- Ornamental grating will be removed for restoration from the upper Langdell roof locations.
During the week of June 28, roofing work will commence on Areeda Hall.