What’s the latest work going on up on the roof? Here’s what’s happening at the end of this month:
- Parapet masonry work from the aerial lifts will continue on the west sides of Langdell Hall at Areeda Hall and will continue daily until the end of next week. The aerial lift will be moving to the east sides of Langdell Hall by Holmes field for the week of August 24. The current plan, weather permitting, is to be completed with aerial lift work by the last week in August.
- Copper roofing is underway on Areeda Hall and on the Langdell Hall north and south lower roofs and will be completed by the end of next week.
- Copper roofing is underway at Areeda Hall and will be completed by the end of next week.
Check out the photo in this post to view the progress and contrast the shiny new copper over the Langdell North classroom area with the older green copper still on the main portion of the roof.